In 2017 Part 8 development was granted for works to be completed in Caherconlish village.
The following improvement works have been completed:
- Raised pedestrian crossings at Lynch's Cross and the Library on the R513
- The build out onto High street off the R513
- Improvements to the public lighting
It is planned to carry out further works during Summer / Autumn 2019 including:
- The buildout at Lynch's pub
- Footpath linkage to Cois Riaga housing estate
- Fully raised junction at Lynch's cross
- Setting back of existing boundaries opposite Lynch's pub, surface water drainage and footpath construction